Escambia County Flood Recovery: Six-Month Report


  • November 3, 2014
  • /   Jack Brown
  • /   civiccon
Six months after the rain began to fall on April 29, the sheer scope of the flood’s impact on Escambia County is staggering. One resident lost her life, hundreds were displaced from their homes and entire neighborhoods were torn apart by the rising waters. As of the end of September, 466 Escambia County residents are still displaced from their homes as a result of the devastating floods. In all, the floods caused an estimated $90 million in damage to the County’s infrastructure and facilities. The science tells the story. The National Weather Service estimates show that more than 25 inches of rain fell in 24 hours – the highest amount of rainfall recorded since 1879, with the heaviest rains soaking the urbanized areas of the County, south of Well Line Road. An astounding six inches of rain was recorded in a single hour at the airport in the southeast area of the City of Pensacola between 9 and 10 p.m. Today, Escambia County is hard at work repairing roads and bridges so that they are better and stronger than they were before the storm. Almost 80 percent of the 2,318 infrastructure damage sites identified after April’s flood have already been addressed or repaired. An additional 17 percent of the damage sites are currently under design or repair. Escambia County was able to move quickly to return our streets, parks and facilities to near-normal conditions on our own, without having to wait for federal assistance thanks to the confidence our residents placed in their local government with the passage of local option sales tax. That support, coupled with responsible financial management of taxpayer money exercised by the Board of County Commissioners, allowed the Board to authorize a $10 million interest-free loan from the LOST III Fund to the Disaster Recovery Fund to kick-start recovery efforts. From past experience, County leaders knew that a substantial portion of the recovery costs would come due prior to receipt of any reimbursements from the Federal Emergency Management Administration or State Department of Emergency Management. In preparation for these necessary expenses, the Board approved the interfund loan this past July to help in covering the large costs associated with ongoing recovery. To finance the recovery, the cash will be transferred from the LOST III Fund when needed and repaid when FEMA and State DEM reimbursements are made. The April floods impacted nearly all aspects of our community, from individuals and families to businesses, the economy, parks, public buildings and infrastructure. In turn, the recovery process has required an extraordinary effort from the whole community. The County is working to shape these efforts into a cohesive long-term strategy for recovery that:
  • — Simultaneously incorporates immediate needs and the long-term vision of the community.
  • Incorporates “lessons learned” to reduce potential impacts from future disasters.
  • Uses available technical and financial resources to reach the desired outcomes.
— The flood extracted a great toll on infrastructure throughout the area. Transportation, utilities and public facilities were all significantly impacted. In total, the damage assessment area covers approximately 175 square miles (not including 23 square miles located in the City of Pensacola). For a disaster of this size, scope and complexity, recovery requires a multi-faceted approach. To this end, the County: — Focused initial efforts on restoring basic services through infrastructure repair, both temporary and permanent. Infrastructure serves as the foundation for basic public services – water, electricity, transportation and access to homes and businesses –that allowed residents and businesses to begin moving forward with their personal recovery.
  • — Worked to establish multiple points of contact with representatives from FEMA to assist residents in obtaining immediate financial assistance.
  • — Joined with the City of Pensacola to establish a storm water task force to create a multi-disciplinary approach to storm water recovery that includes engagement from technical experts and representatives from all constituencies to identify and institute mitigation and resiliency initiatives.
  • Is working with the owners of Forest Creek Apartments and FEMA to potentially relocate the apartment complex due to repetitive flooding. The property would then be absorbed into the adjacent Jones Creek watershed.
  • — Conducted more than $60,000 in emergency pumping projects to remove storm water from several neighborhoods that continued to hold flood waters for up to two weeks post-event due to their topography. Neighborhoods receiving this type of assistance included:
    • Ponderosa Drive and Surrey Drive near Nine Mile Road
    • Gulf Beach Highway near Nassau Street
    • 73rd Street at Fabiano Street
— Investigated and identified more than 2,300 sites where infrastructure was damaged. Permanently or temporarily addressed or repaired 1,837 of the damaged sites and currently working on another 402 sites. More than $6.6 million has been encumbered to fund project contracts, with $2.8 million expended. Among these projects are:
  • Blue Springs Drive/Crescent Lake Repairs: Substantial storm water runoff washed out segments of Blue Springs Drive and private property over a 2,000-foot pathway between East Shore Drive and Clearwater Avenue. Roadway washouts exceeded 10 feet in depth and cut off access to approximately 30 homes. Escambia County Public Works, working jointly with contractors and local utility crews, were able to provide temporary access as quickly as two weeks after the storm. Within five weeks, temporary roadway and utility repairs were complete. More than $400,000 has been spent on emergency repairs and construction of $560,000 in permanent repairs is underway.
  • Johnson Avenue Repairs: The east end of Johnson Avenue near Olive Road was washed out at a major culvert crossing, leaving a 20-foot deep gap in the roadway. Design and construction of temporary repairs were completed within 12 weeks post-event at a cost of $500,000, providing access to the nearly 5,000 vehicles that use this portion of the road each day.
  • Galvin Avenue Repairs: An overwhelmed storm water system at Galvin Avenue in the Springdale Forest area washed out, cutting off access to 28 properties and destroying one home. More than $45,000 in temporary roadway and utility repairs were completed within three weeks of the flood, providing property owners with access to their homes. Construction of permanent repairs will commence shortly.
  • County Storm Water Pond Repair: Repair work to the more than 110 retention ponds locations with reported damage began the day after the flood, with 50 sites repaired by County crews at a cost of more than $475,000. An additional 30 sites are currently under contract for approximately $600,000 in engineering design and repair work.
Throughout the history of Escambia County, we have persisted through natural disasters – hurricanes, wildfires, oil spills, ice storms and floods. The flood of April 2014 once again demonstrated the resiliency of our community and its people. We have learned from what has happened. We have a plan to move forward and we will recover on our own terms. That’s our commitment to the residents and neighborhoods impacted by the flood. We will continue to support efforts to rebuild by providing the financial resources and professional expertise needed for a full recovery.
Your items have been added to the shopping cart. The shopping cart modal has opened and here you can review items in your cart before going to checkout